Friday, March 11, 2011

Friday Update from the Construction Site

3/11 - Both inspections schduled for today passed.
Next week:
3/14 – Backfill
3/15 – Slab Prep
3/16 -  Pour Slab (Slab Prep Inspection to follow soon after)  
3/16 – Lumber arrives on site
3/17 – Framing Begins

Thursday, March 10, 2011

Inspections Set for Tomorrow

Inspection Type                                                          Schedule Date

103 - Foundation Damp Proofing                            3/11/2011
104 – Drain Tile with Foundation Inspection           3/11/2011

Tuesday, March 8, 2011

3/2/2011-3/6/2011

3/2/2011-3/6/2011
During this time:
            -Dug Hole
            -Formed and Poured Footers
            -Baltimore County Inspection 101, Footings – PASSED on 3/4/2011.