Tuesday, March 8, 2011

3/4-PM (Project Manager) Update, Approximate Timeline for the week.

3/8 - Form and pour walls
3/9 - Strip forms
3/10 - Water proofing
3/11 - Install exterior drain tile. Plumber will do ground work – will order inspection.
3/14 - Backfill