Monday, March 28, 2011

Pre Drywall Meeting

Framing nearly complete.  HVAC roughed in.  Electical and plumbing are being worked on today and tomorrow.  My independent inspection is Wednesday.  Pleantly of pictures, take a look.
















Saturday, March 19, 2011

Framing Day 2

Ryan Homes starting on Day 2 of Framing.

Front View, Venice Model, Reverse Floor Plan

Day 2, Venice Model, Framing
View into Garage, Venice Model

Friday, March 18, 2011

Framing Day 1

Images from the first day of framing.


Ryan Homes, Venice Model, Framing Day 1
Front View, Garage Entrance on Left
Side View

Friday, March 11, 2011

Friday Update from the Construction Site

3/11 - Both inspections schduled for today passed.
Next week:
3/14 – Backfill
3/15 – Slab Prep
3/16 -  Pour Slab (Slab Prep Inspection to follow soon after)  
3/16 – Lumber arrives on site
3/17 – Framing Begins